Summerland - Prairie Creek Stormwater Diversion Works

Summerland, British Columbia

completeWastewaterCC
Federal contribution
$250,982
Federal share33%

of $753.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 24, 2012
201220132014
Built

Approved 4 months before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
District of Summerland
Construction start
Sep 12, 2012(actual)
Construction end
Mar 31, 2014(actual)

Against the original forecast

  • Construction start4 months earlyforecast Jan 1, 2013

Also in Summerland

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41703 in the federal list. How to read these figures.