Container Yard Paving - Fraser Surrey Docks
Federal contribution
$1.5M
$1,452,461
Federal share48%
of $3.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 4, 2011
2011
Built
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Vancouver Fraser Port Authority
- Construction start
- Dec 6, 2010(actual)
- Construction end
- Oct 31, 2011(actual)
Against the original forecast
- Construction start7 weeks lateforecast Oct 15, 2010
- Construction end4 weeks lateforecast Oct 1, 2011
Also in Surrey
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41775 in the federal list. How to read these figures.