Sidewalk Addition to Fairmont Bridge on Highway 93/95
Fairmont Hot Springs, British Columbia
Federal contribution
$201,111
Federal share49%
of $407.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 8, 2011
Built
Approved 6 months before the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Government of British Columbia
- Construction start
- Mar 1, 2011(actual)
- Construction end
- Jun 30, 2011(actual)
Against the original forecast
- Construction start2 weeks earlyforecast Mar 16, 2011
- Construction end4 weeks lateforecast May 31, 2011
Also in Fairmont Hot Springs
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41930 in the federal list. How to read these figures.