East Kootenay - Cold Spring Creek Debris Flow Mitigation Phase 2
Fairmont Hot Springs, British Columbia
Federal contribution
$7.8M
$7,778,398
Federal share80%
of $9.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 5, 2022
20222023202420252026
Built
Approved 16 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Regional District of East Kootenay
- Construction start
- Sep 11, 2023(actual)
- Construction end
- Dec 31, 2025(actual)
Against the original forecast
- Construction start7 weeks lateforecast Jul 26, 2023
- Construction end3 weeks lateforecast Dec 13, 2025