Expansion of Service d’entraide du Patro Roc-Amadour

Québec, Quebec

completeRecreationISF
Federal contribution
$1.4M
$1,406,357
Federal share33%

of $4.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedOct 1, 2010
2011
Built

Approved 4 weeks before the announcement.

Program
Infrastructure Stimulus Fund
Ultimate recipient
Patro Roc-Amadour Inc.
Construction start
Sep 27, 2010(actual)
Construction end
Oct 14, 2011(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 1, 2010
  • Construction end2 weeks earlyforecast Oct 31, 2011

Also in Québec

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 41999 in the federal list. How to read these figures.