Harrington Community Centre Renovations
Federal contribution
$62,333
Federal share33%
of $187.0K total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJan 24, 2011
ApprovedMar 4, 2011
2011
Built
Approved 6 weeks after the announcement.
- Program
- Infrastructure Stimulus Fund
- Ultimate recipient
- Municipality of L'Isle-aux-Allumettes
- Construction start
- Jan 1, 2011(actual)
- Construction end
- Aug 1, 2011(actual)
Against the original forecast
- Construction start2 months lateforecast Nov 1, 2010
Also in L'Isle-aux-Allumettes
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 42008 in the federal list. How to read these figures.