Water Systems Upgrades
Federal contribution
$1.7M
$1,662,453
Federal share40%
of $4.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2020
2021202220232024
Built
Approved 4 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- L'Isle-aux-Allumettes
- Construction start
- Jun 1, 2023(actual)
- Construction end
- May 31, 2024(actual)
Against the original forecast
- Construction start22 months lateforecast Aug 2, 2021
- Construction end5 months lateforecast Jan 8, 2024