Biomethanation and composting project by the City of Saint-Hyacinthe

Saint-Hyacinthe, Quebec

completeSolid Waste ManagementGIF
Federal contribution
$11.4M
$11,387,011
Federal share33%

of $34.2M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 26, 2012
201320142015201620172018
Built

Approved 3 months after the announcement.

Program
Green Infrastructure Fund
Ultimate recipient
City of Saint-Hyacinthe
Construction start
Aug 8, 2013(actual)
Construction end
Nov 21, 2017(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 25, 2012
  • Construction end6 weeks earlyforecast Dec 31, 2017

Also in Saint-Hyacinthe

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43118 in the federal list. How to read these figures.