Biomethanation and composting project by the City of Saint-Hyacinthe
Federal contribution
$11.4M
$11,387,011
Federal share33%
of $34.2M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 26, 2012
201320142015201620172018
Built
Approved 3 months after the announcement.
- Program
- Green Infrastructure Fund
- Ultimate recipient
- City of Saint-Hyacinthe
- Construction start
- Aug 8, 2013(actual)
- Construction end
- Nov 21, 2017(actual)
Against the original forecast
- Construction start9 months lateforecast Oct 25, 2012
- Construction end6 weeks earlyforecast Dec 31, 2017
Also in Saint-Hyacinthe
- Wastewater Treatment Plant Upgrade$24.9M
- Upgrading the Filtration Plant$6.9M
- Construction of a recreation/aquatic centre$5.3M
- Railway grading project (grade-separation) in the extension of boulevard Casavant in Saint-Hyacinthe$4.0M
- Renovation of the 11th into a 20-bed care unit and a 12-bed intervention and brief hospitalization unit at Hôpital Honoré Mercier$1.8M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43118 in the federal list. How to read these figures.