Railway grading project (grade-separation) in the extension of boulevard Casavant in Saint-Hyacinthe

Saint-Hyacinthe, Quebec

completeHighways and RoadsSCF
Federal contribution
$4.0M
$4,000,000
Federal share33%

of $12.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedSep 18, 2017
20182019202020212022
Built

Approved 2 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
City of Saint-Hyacinthe
Construction start
Oct 23, 2017(actual)
Construction end
Dec 16, 2021(actual)

Against the original forecast

  • Construction start7 weeks lateforecast Sep 4, 2017
  • Construction end3 years lateforecast Dec 21, 2018