Niagara-On-the-Lake Wastewater Treatment Plant

Niagara-on-the-Lake, Ontario

completeWastewaterMIC
Federal contribution
$14.4M
$14,426,667
Federal share33%

of $43.3M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedAug 28, 2012
ApprovedSep 30, 2013
2013201520172019
Built

Approved 13 months after the announcement.

Program
Building Canada Fund - Major Infrastructure Component
Construction start
Apr 2, 2015(actual)
Construction end
Jan 17, 2020(actual)

Against the original forecast

  • Construction start9 months lateforecast Jun 30, 2014
  • Construction end2 months earlyforecast Mar 31, 2020