Line 3 Road asbestos clay watermain upgrade
Federal contribution
$176,670
Federal share45%
of $391.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 27, 2017
2018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Town of Niagara-on-the-Lake
- Construction start
- Dec 4, 2017(actual)
- Construction end
- May 31, 2018(actual)
Against the original forecast
- Construction start8 months lateforecast Apr 1, 2017
Also in Niagara-on-the-Lake