Saint-Apollinaire Multipurpose Centre
Federal contribution
$3.2M
$3,230,000
Federal share44%
of $7.3M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 25, 2012
ApprovedSep 20, 2013
2013201420152016
Built
Approved 14 months after the announcement.
- Program
- Building Canada Fund - Major Infrastructure Component
- Ultimate recipient
- Municipality of Saint-Apollinaire
- Construction start
- Jun 1, 2014(actual)
- Construction end
- Mar 31, 2016(actual)
Also in Saint-Apollinaire
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 43745 in the federal list. How to read these figures.