Development of a refrigerated and covered ice rink
Federal contribution
$1.4M
$1,356,723
Federal share33%
of $4.1M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 23, 2021
20212022
Built
Approved 3 months before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Municipality of Saint-Apollinaire
- Construction start
- Oct 25, 2021(actual)
- Construction end
- Oct 31, 2022(actual)