Victiria View Lane to Langley Subdivision Water Interconnection

Stratford, Prince Edward Island

completeDrinking WaterCC
Federal contribution
$45,945
Federal share32%

of $145.0K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201420152016
Built

Approved 2.9 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
Town of Stratford
Construction start
Jul 2, 2013(actual)
Construction end
Sep 9, 2013(actual)

Against the original forecast

  • Construction start8 weeks lateforecast May 7, 2013

Also in Stratford

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44170 in the federal list. How to read these figures.