Charlottetown - Miltonvale Municipal Well Drilling
Charlottetown, Prince Edward Island
Federal contribution
$232,058
Federal share33%
of $696.2K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201420152016
Built
Approved 2.8 years before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- City of Charlottetown
- Construction start
- Oct 15, 2013(actual)
- Construction end
- Dec 1, 2015(actual)
Against the original forecast
- Construction start5 months lateforecast May 15, 2013
- Construction end3 months lateforecast Aug 30, 2015