Back to projects

Charlottetown - Miltonvale Municipal Well Drilling

Charlottetown, Prince Edward Island

completeDrinking WaterCC
Federal contribution
$232,058
Federal share33%

of $696.2K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201420152016
Built

Approved 2.8 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Charlottetown
Construction start
Oct 15, 2013(actual)
Construction end
Dec 1, 2015(actual)

Against the original forecast

  • Construction start5 months lateforecast May 15, 2013
  • Construction end3 months lateforecast Aug 30, 2015

Also in Charlottetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44190 in the federal list. How to read these figures.