Charlottetown - Miltonvale Wellfield Piping & Water Supply Building

Charlottetown, Prince Edward Island

completeDrinking WaterCC
Federal contribution
$405,253
Federal share31%

of $1.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201420152016
Built

Approved 2.5 years before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Charlottetown
Construction start
Sep 8, 2014(actual)
Construction end
Dec 1, 2015(actual)

Against the original forecast

  • Construction start4 months lateforecast May 15, 2014
  • Construction end3 months lateforecast Aug 30, 2015