Wastewater Treatment, Phase 5 - Plage du Foulon
Federal contribution
$9.9M
$9,878,439
Federal share33%
of $29.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 1, 2017
2017201920212023
Built
Approved 11 months before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Québec
- Construction start
- Jun 22, 2016(actual)
- Construction end
- Mar 31, 2023(actual)
Against the original forecast
- Construction start3 months lateforecast Mar 9, 2016
- Construction end21 months earlyforecast Dec 20, 2024