Upgrade of the Sarnia Wastewater Collection System

Sarnia, Ontario

completeWastewaterCSIF
Federal contribution
$17.5M
$17,487,495
Federal share50%

of $35.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedJul 5, 2007
ApprovedSep 3, 2008
200820092010201120122013
Built

Approved 14 months after the announcement.

Program
Canada Strategic Infrastructure Fund
Construction start
Mar 15, 2008(actual)
Construction end
Mar 22, 2013(actual)

Also in Sarnia

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44512 in the federal list. How to read these figures.