Upgrade of the Sarnia Wastewater Collection System
Federal contribution
$17.5M
$17,487,495
Federal share50%
of $35.0M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 5, 2007
ApprovedSep 3, 2008
200820092010201120122013
Built
Approved 14 months after the announcement.
- Program
- Canada Strategic Infrastructure Fund
- Ultimate recipient
- Corporation of the City of Sarnia.
- Construction start
- Mar 15, 2008(actual)
- Construction end
- Mar 22, 2013(actual)
Also in Sarnia
- City of Sarnia Sewer Upgrade$15.0M
- Cromwell area Sewer Separation and Flood Mitigation$12.0M
- Combined Sewer Separation - Flooding and Overflow Mitigation$10.4M
- Lambton College Centre for Health Education and Sustainable Care (CHESC)$9.0M
- Purchase of zero emission vehicles and installation of charging stations to provide transit services in and around the City of Sarnia, Ontario$4.9M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44512 in the federal list. How to read these figures.