City of Sarnia Sewer Upgrade

Sarnia, Ontario

completeWastewaterSCF
Federal contribution
$15.0M
$15,008,616
Federal share33%

of $45.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2015
20162018202020222024
Built

Approved 6 weeks before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Apr 11, 2016(actual)
Construction end
Sep 19, 2023(actual)

Against the original forecast

  • Construction start6 weeks lateforecast Mar 1, 2016
  • Construction end11 months lateforecast Oct 31, 2022