City of Sarnia Sewer Upgrade
Federal contribution
$15.0M
$15,008,616
Federal share33%
of $45.0M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedJul 30, 2015
20162018202020222024
Built
Approved 6 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Corporation of the City of Sarnia.
- Construction start
- Apr 11, 2016(actual)
- Construction end
- Sep 19, 2023(actual)
Against the original forecast
- Construction start6 weeks lateforecast Mar 1, 2016
- Construction end11 months lateforecast Oct 31, 2022
Also in Sarnia
- Upgrade of the Sarnia Wastewater Collection System$17.5M
- Cromwell area Sewer Separation and Flood Mitigation$12.0M
- Combined Sewer Separation - Flooding and Overflow Mitigation$10.4M
- Lambton College Centre for Health Education and Sustainable Care (CHESC)$9.0M
- Purchase of zero emission vehicles and installation of charging stations to provide transit services in and around the City of Sarnia, Ontario$4.9M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46198 in the federal list. How to read these figures.