QC Autoroute 55

Stanstead, Quebec

completeBorder InfrastructureBIF
Federal contribution
$7.4M
$7,375,886
Federal share49%

of $15.0M total eligible cost; the rest comes from other partners.

Schedule

AnnouncedApr 29, 2005
ApprovedApr 26, 2006
20052007200920112013
Built

Approved 12 months after the announcement.

Program
Border Infrastructure Fund
Ultimate recipient
Province of Quebec
Construction start
Aug 1, 2007(actual)
Construction end
Nov 11, 2013(actual)

Against the original forecast

  • Construction end12 months lateforecast Oct 31, 2012

Also in Stanstead

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44625 in the federal list. How to read these figures.