Connection of the ST-PE-3-13 well to Stanstead's drinking water system

Stanstead, Quebec

completeDrinking WaterCWWF
Federal contribution
$755,120
Federal share50%

of $1.5M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 28, 2017
20182019
Built

Approved 2 months before the announcement.

Program
Clean Water and Wastewater Fund
Ultimate recipient
Town of Stanstead
Construction start
Mar 29, 2018(actual)
Construction end
Sep 30, 2019(actual)

Against the original forecast

  • Construction start5 weeks earlyforecast May 1, 2018
  • Construction end4 weeks earlyforecast Oct 31, 2019