Vernon - Okanagan Landing Flood Protection - Phase 2

Vernon, British Columbia

completeDisaster MitigationCC
Federal contribution
$697,727
Federal share33%

of $2.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMay 2, 2014
20152016
Built

Approved 5 weeks before the announcement.

Program
Building Canada Fund - Communities Component
Ultimate recipient
City of Vernon
Construction start
Jul 20, 2015(actual)
Construction end
Mar 31, 2016(actual)

Against the original forecast

  • Construction start10 months lateforecast Sep 16, 2014
  • Construction end4 months lateforecast Dec 15, 2015

Also in Vernon

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44872 in the federal list. How to read these figures.