Nicomen Island - Athey Road Dike Protection/Bank Stabilization Phase II
Federal contribution
$101,815
Federal share33%
of $307.1K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 2, 2014
2015
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Nicomen Island Improvement District
- Construction start
- Jan 15, 2015(actual)
- Construction end
- Sep 30, 2015(actual)
Against the original forecast
- Construction start2 months lateforecast Nov 1, 2014
Also in Mission
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 44884 in the federal list. How to read these figures.