Mission - Hatzic Valley Pumping Station Upgrade
Federal contribution
$165,616
Federal share26%
of $625.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 2, 2014
20152016
Built
Approved 5 weeks before the announcement.
- Program
- Building Canada Fund - Communities Component
- Ultimate recipient
- Dewdney Area Improvement District
- Construction start
- Aug 30, 2015(actual)
- Construction end
- Mar 31, 2016(actual)
Against the original forecast
- Construction start12 months lateforecast Aug 15, 2014
Also in Mission