Kicking Horse Canyon Project Phase 4: West Portal to Yoho Bridge

Golden, British Columbia

completeHighways and RoadsNIC
Federal contribution
$215.2M
$215,198,500
Federal share40%

of $543.3M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedFeb 17, 2017
2017201920212023
Built

Approved 4 weeks before the announcement.

Program
National Infrastructure Component
Construction start
Nov 6, 2020(actual)
Construction end
Jul 31, 2024(actual)

Against the original forecast

  • Construction end2 months lateforecast May 31, 2024