Trans-Canada Highway 1 - Quartz Creek
Federal contribution
$49.9M
$49,924,542
Federal share50%
of $99.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 28, 2019
today
20192021202320252027
BuiltForecast
Approved 7 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- British Columbia Ministry of Transportation and Infrastructure
- Construction start
- May 3, 2021(actual)
- Construction end
- Sep 30, 2026(forecast)
Against the original forecast
- Construction start5 weeks lateforecast Mar 31, 2021
Also in Golden
- Kicking Horse Canyon Project Phase 4: West Portal to Yoho Bridge$215.2M
- Kicking Horse Canyon Highway Improvement Project - Phase 2$62.5M
- Highway 1 Selkirk Mountain Four-Laning$31.5M
- TOWN OF GOLDEN: FLOOD RESILIENCE HIGHWAY 95, KICKING HORSE I & II BRIDGE$28.8M
- Kicking Horse Canyon - Brake Check to Yoho$28.3M
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52272 in the federal list. How to read these figures.