Optimization of Port of Montreal Capacity

Montréal, Quebec

completeMarineNIC
Federal contribution
$43.7M
$43,666,667
Federal share33%

of $132.0M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJan 20, 2015
201520172019202120232025
Built

Approved 4 weeks before the announcement.

Program
National Infrastructure Component
Ultimate recipient
Montreal Port Authority
Construction start
Sep 15, 2015(actual)
Construction end
Aug 26, 2024(actual)

Against the original forecast

  • Construction start3 months lateforecast Jun 1, 2015
  • Construction end4 months earlyforecast Dec 31, 2024