Highway No. 7 & Passing Lanes: Delisle to Rosetown
Federal contribution
$3.8M
$3,835,000
Federal share50%
of $7.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedSep 11, 2014
2015
Built
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Province of Saskatchewan
- Construction start
- Sep 2, 2014(actual)
- Construction end
- Jul 7, 2015(actual)
Against the original forecast
- Construction start4 weeks earlyforecast Sep 30, 2014
- Construction end6 months earlyforecast Dec 31, 2015
Also in Rosetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45746 in the federal list. How to read these figures.