Town of Rosetown - Rosetown Landfill Decommissioning
Federal contribution
$542,973
Federal share40%
of $1.4M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 27, 2022
20222023202420252026
Built
Approved 3 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Town of Rosetown
- Construction start
- Oct 30, 2024(actual)
- Construction end
- Jan 31, 2026(actual)
Against the original forecast
- Construction start7 months lateforecast Apr 1, 2024
- Construction end4 weeks lateforecast Dec 31, 2025
Also in Rosetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61309 in the federal list. How to read these figures.