Rehabilitation of water services and splitting of water networks in several areas

Gatineau, Quebec

completeWastewaterLUCC
Federal contribution
$2.9M
$2,925,325
Federal share33%

of $8.8M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
201420152016201720182019
Built

Approved 14 months before the announcement.

Program
Building Canada Fund - Large Urban Centres Component
Ultimate recipient
City of Gatineau
Construction start
Feb 20, 2014(actual)
Construction end
Dec 21, 2018(actual)

Against the original forecast

  • Construction start6 months earlyforecast Sep 1, 2014
  • Construction end3 years lateforecast Dec 31, 2015

Also in Gatineau

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45748 in the federal list. How to read these figures.