Rehabilitation of water services and splitting of water networks in several areas
Federal contribution
$2.9M
$2,925,325
Federal share33%
of $8.8M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201420152016201720182019
Built
Approved 14 months before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Gatineau
- Construction start
- Feb 20, 2014(actual)
- Construction end
- Dec 21, 2018(actual)
Against the original forecast
- Construction start6 months earlyforecast Sep 1, 2014
- Construction end3 years lateforecast Dec 31, 2015
Also in Gatineau
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45748 in the federal list. How to read these figures.