Iqaluit Marine Infrastructure

Iqaluit, Nunavut

completeMarineNRP
Federal contribution
$63.7M
$63,700,000
Federal share75%

of $84.9M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 30, 2015
2016201820202022
Built
Program
Provincial-Territorial Infrastructure Component - National and Regional Projects
Construction start
Jul 29, 2018(actual)
Construction end
Sep 9, 2022(actual)

Against the original forecast

  • Construction start13 months lateforecast Jul 1, 2017
  • Construction end7 weeks earlyforecast Oct 31, 2022

Also in Iqaluit

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45787 in the federal list. How to read these figures.