Iqaluit Solid Waste Facilities - Phase 1

Iqaluit, Nunavut

underwaySolid Waste ManagementGIS
Federal contribution
$21.1M
$21,080,021
Federal share75%

of $28.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedJul 20, 2018
today
201920212023202520272029
BuiltForecast

Approved 3 weeks before the announcement.

Program
Green Infrastructure Stream
Ultimate recipient
City of Iqaluit
Construction start
Sep 23, 2020(actual)
Construction end
Dec 31, 2028(forecast)

Against the original forecast

  • Construction start3 months lateforecast Jul 1, 2020

Also in Iqaluit

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 52618 in the federal list. How to read these figures.