Rehabilitation of Dorimène-Desjardins and Saint-Louis streets (Lévis sector)
Federal contribution
$1.2M
$1,230,551
Federal share33%
of $3.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
201520162017
Built
Approved 10 months before the announcement.
- Program
- Building Canada Fund - Large Urban Centres Component
- Ultimate recipient
- City of Lévis
- Construction start
- Nov 1, 2014(actual)
- Construction end
- Feb 28, 2017(actual)
Against the original forecast
- Construction start3 months earlyforecast Feb 2, 2015
- Construction end14 months lateforecast Dec 31, 2015
Also in Lévis