Northwest Territories - Capacity Building
Yellowknife, Northwest Territories
Federal contribution
$160,000
Federal share50%
of $320.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMar 15, 2016
20082010201220142016
Built
Approved 8 years before the announcement.
- Program
- Municipal Rural Infrastructure Fund
- Ultimate recipient
- MACA
- Construction start
- Apr 1, 2008(actual)
- Construction end
- Mar 21, 2012(actual)
Against the original forecast
- Construction start2.8 years lateforecast Jun 29, 2005
- Construction end12 months lateforecast Mar 31, 2011