Aquaduct liner for various streets in 2015

Salaberry-de-Valleyfield, Quebec

completeWastewaterCC
Federal contribution
$539,482
Federal share33%

of $1.6M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 15, 2016
2016
Built

Approved 10 months before the announcement.

Program
Building Canada Fund - Communities Component
Construction start
Sep 25, 2015(actual)
Construction end
Mar 29, 2016(actual)

Against the original forecast

  • Construction start8 weeks lateforecast Aug 3, 2015
  • Construction end5 months lateforecast Oct 30, 2015