Pugwash and Area Water Supply
Federal contribution
$4.9M
$4,922,418
Federal share33%
of $14.9M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJul 29, 2015
ApprovedJan 15, 2016
2016201720182019
Built
Approved 6 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Municipality of the County of Cumberland
- Construction start
- Jul 27, 2016(actual)
- Construction end
- Feb 13, 2019(actual)
Against the original forecast
- Construction start8 weeks lateforecast Jun 2, 2016
- Construction end16 months lateforecast Sep 30, 2017
Also in Cumberland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45980 in the federal list. How to read these figures.