Municipality of the County of Cumberland - Springhill Junction Road and Athol Road
Federal contribution
$2.6M
$2,582,800
Federal share40%
of $6.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedFeb 25, 2023
2023
Built
Approved 2 months before the announcement.
- Program
- Green Infrastructure Stream
- Ultimate recipient
- Municipality of the County of Cumberland
- Construction start
- Jun 16, 2023(actual)
- Construction end
- Dec 8, 2023(actual)
Against the original forecast
- Construction start2 weeks lateforecast Jun 1, 2023
Also in Cumberland
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 65825 in the federal list. How to read these figures.