Pond Inlet Marine Infrastructure
Federal contribution
$30.0M
$30,000,000
Federal share73%
of $41.2M total eligible cost; the rest comes from other partners.
Schedule
AnnouncedJun 26, 2015
ApprovedMar 9, 2016
2016201820202022
Built
Approved 8 months after the announcement.
- Program
- Provincial-Territorial Infrastructure Component - National and Regional Projects
- Ultimate recipient
- Nunavut Ministry of Community and Government Services
- Construction start
- Aug 4, 2018(actual)
- Construction end
- Oct 25, 2021(actual)
Against the original forecast
- Construction start16 months lateforecast Apr 4, 2017
- Construction end2 months earlyforecast Dec 31, 2021