Schedule
Announced and approvedFeb 15, 2023
202320242025
BuiltForecast
Approved 2 months before the announcement.
- Program
- Green and Inclusive Community Buildings Program
- Ultimate recipient
- Hamlet of Pond Inlet
- Construction start
- Apr 1, 2022(actual)
- Construction end
- Jun 15, 2025(forecast)
Against the original forecast
- Construction start5 months earlyforecast Sep 15, 2022