East St. Paul Water Reservoir Expansion: Additional Capacity & Raw Water Treatment
Federal contribution
$500,000
Federal share33%
of $1.5M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedOct 31, 2014
201520162017
Built
Approved 3 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Rural Municipality of East St. Paul
- Construction start
- Jul 13, 2016(actual)
- Construction end
- Mar 24, 2017(actual)
Against the original forecast
- Construction end12 months earlyforecast Mar 31, 2018
Also in East St. Paul
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 45996 in the federal list. How to read these figures.