Sewage Treatment Plant Upgrade: Feasibility Study
Federal contribution
$34,990
Federal share47%
of $75.0K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 18, 2017
2018
Built
Approved 8 weeks before the announcement.
- Program
- Clean Water and Wastewater Fund
- Ultimate recipient
- Rural Municipality of East St. Paul
- Construction start
- Dec 12, 2017(actual)
- Construction end
- Mar 31, 2018(actual)
Against the original forecast
- Construction end2 weeks lateforecast Mar 15, 2018
Also in East St. Paul
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 49290 in the federal list. How to read these figures.