Colonel Gray Sewershed Rehabilitation
Charlottetown, Prince Edward Island
Federal contribution
$877,476
Federal share33%
of $2.7M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 4, 2016
201620172018
Built
Approved 11 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- City of Charlottetown
- Construction start
- Aug 11, 2016(actual)
- Construction end
- Aug 10, 2018(actual)
Against the original forecast
- Construction start11 months lateforecast Aug 30, 2015
- Construction end7 months earlyforecast Feb 28, 2019