Cavendish Lagoon Upgrades

Resort Municipality, Prince Edward Island

completeWastewaterSCF
Federal contribution
$118,958
Federal share24%

of $488.4K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedApr 4, 2016
20162017
Built

Approved 11 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Construction start
Jul 1, 2016(actual)
Construction end
Mar 14, 2017(actual)

Against the original forecast

  • Construction start9 months lateforecast Oct 1, 2015
  • Construction end7 months earlyforecast Sep 30, 2017