Replace 4 Picnic Shelters at Montgomery Park
Resort Municipality, Prince Edward Island
Federal contribution
$33,095
Federal share25%
of $130.3K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 5, 2021
2022
Built
Approved 4 weeks before the announcement.
- Program
- Community, Culture & Recreation Infrastructure Stream
- Ultimate recipient
- Community of Resort Municipality
- Construction start
- Nov 15, 2021(actual)
- Construction end
- Jul 5, 2022(actual)
Against the original forecast
- Construction start2 weeks lateforecast Nov 1, 2021
- Construction end6 months lateforecast Dec 31, 2021
Also in Resort Municipality
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61035 in the federal list. How to read these figures.