Back to projects

Replace 4 Picnic Shelters at Montgomery Park

Resort Municipality, Prince Edward Island

completeRecreationCCRIS
Federal contribution
$33,095
Federal share25%

of $130.3K total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedAug 5, 2021
2022
Built

Approved 4 weeks before the announcement.

Program
Community, Culture & Recreation Infrastructure Stream
Construction start
Nov 15, 2021(actual)
Construction end
Jul 5, 2022(actual)

Against the original forecast

  • Construction start2 weeks lateforecast Nov 1, 2021
  • Construction end6 months lateforecast Dec 31, 2021

Also in Resort Municipality

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 61035 in the federal list. How to read these figures.