MacPhee Avenue Sanitary Sewer Upgrades
Federal contribution
$32,132
Federal share25%
of $127.5K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedApr 4, 2016
2016
Built
Approved 11 months before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Souris
- Construction start
- Nov 1, 2015(actual)
- Construction end
- Dec 15, 2015(actual)
Against the original forecast
- Construction start5 months lateforecast Jun 1, 2015
- Construction end2 months lateforecast Sep 30, 2015
Also in Souris
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46029 in the federal list. How to read these figures.