Schedule

Announced and approvedJul 30, 2015
20162017
Built

Approved 3 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Saint-Isidore
Construction start
Aug 9, 2016(actual)
Construction end
Jul 31, 2017(actual)

Against the original forecast

  • Construction start7 weeks earlyforecast Sep 26, 2016
  • Construction end4 weeks lateforecast Jun 30, 2017