Bike Lane
Federal contribution
$205,635
Federal share60%
of $342.7K total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 28, 2024
20232024
Built
Approved 2.1 years before the announcement.
- Program
- Active Transportation Fund
- Ultimate recipient
- Municipality of Hautes-Terres
- Construction start
- Nov 1, 2023(actual)
- Construction end
- Dec 10, 2023(actual)
Against the original forecast
- Construction start17 months lateforecast Jun 6, 2022
- Construction end11 months lateforecast Dec 30, 2022
Also in St-Isidore