Storm Drain System Reconstruction

Gagetown, New Brunswick

completeWastewaterSCF
Federal contribution
$379,547
Federal share33%

of $1.1M total eligible cost; the rest comes from other partners.

Schedule

Announced and approvedMar 16, 2016
2016201820202022
Built

Approved 10 months before the announcement.

Program
Provincial-Territorial Infrastructure Component - Small Communities Fund
Ultimate recipient
Village of Gagetown
Construction start
May 1, 2016(actual)
Construction end
Nov 24, 2022(actual)

Against the original forecast

  • Construction start2 weeks earlyforecast May 16, 2016
  • Construction end3 weeks lateforecast Oct 31, 2022

Also in Gagetown

Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 46045 in the federal list. How to read these figures.