Mill Road Upgrades - Gagetown
Federal contribution
$1.0M
$1,026,098
Federal share66%
of $1.6M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedAug 5, 2021
20212022
Built
Approved 8 months before the announcement.
- Program
- COVID-19 Resilience Stream
- Ultimate recipient
- Village of Gagetown
- Construction start
- Jul 25, 2022(actual)
- Construction end
- Oct 18, 2022(actual)
Against the original forecast
- Construction start2 months lateforecast May 24, 2022
Also in Gagetown
Amounts are federal dollars committed, not spent to date. Status is inferred from the dates above, not reported by the source. Project 58142 in the federal list. How to read these figures.