Ritchie Lake Collector Sewer and Longwood Upgrades
Federal contribution
$2.3M
$2,299,598
Federal share33%
of $6.9M total eligible cost; the rest comes from other partners.
Schedule
Announced and approvedMay 29, 2015
2016201820202022
Built
Approved 2 weeks before the announcement.
- Program
- Provincial-Territorial Infrastructure Component - Small Communities Fund
- Ultimate recipient
- Town of Quispamsis
- Construction start
- Apr 18, 2016(actual)
- Construction end
- Dec 20, 2021(actual)
Against the original forecast
- Construction start5 months lateforecast Nov 15, 2015
- Construction end4 months lateforecast Aug 31, 2021